Renegotiation of power purchasing agreements (PPAs) must be completed by  Nov 30 this year or the country will continue to bleed money into  independent power producers (IPP), the Association of Water and Energy  Research Malaysia (AWER) said today.
Any  delay in renegotiations between the government and IPPs would give the  IPPs leverage to bulldoze exorbitant project bids to build new power  plants on the excuse of lack of time, the NGO said.
Taking  the issue of the recently approved construction of the Manjung and  Tanjung Bin coal-powered plants, AWER said Malakoff Corporation Bhd got  the Tanjung Bin project at RM500 million higher than the first project –  because of the rush to build the power plant.
The  association pointed out that while the Manjung plant project was  awarded to national power company Tenaga Nasional Bhd (TNB), which  submitted the best bid under ‘Compromised Open Bidding’, no fresh bid  was called for the Tanjung Bin plant project.
The  Manjung plant is estimated to cost some RM5.17 billion, including a  US$810 million engineering contract, a 180 million euro procurement  contract and a RM1.8 billion construction contract, according to a TNB  announcement on Bursa Malaysia in April.
Both  power plants are to produce 1,000 megawatts (MW) of power each when  operational, to make up for the potential loss of power supply from the  2,400MW Bakun hydroelectric dam in Sarawak after the state government  decided against supplying power to Peninsular Malaysia as initially  planned.
Delay will cost more money
AWER  pointed out that there are four to five years remaining in the power  purchase deals with to the PPAs, which expire between 2015 and 2016 –  just about enough time for IPPs to set up new power plants under the  current agreement tenure.
This was  essentially the basis for Malakoff’s successful bid to push a higher  price, on grounds that it faced with a “lack of construction time”, the  NGO said.
“This is exactly what (the)  first batch of IPPs are trying to achieve in the ongoing negotiation  process. Therefore, the federal government should not allow this to take  place or it will have to shoulder the responsibility of the failure of  negotiations.”
AWER stressed that the  government was in a position to stop the outflow of cash into IPPs  after the agreement period, provided it settled renegotiations by the  end of next month.
The association  proposed that the government moves towards a transparent process of  reducing the capacity payment to IPPs from 2012 onwards, based on  audited operational costs, engineering reports and a regulated profit  margin.
Shift to licensing regime
Should  the IPPs agree to reduce capacity payments, the government should then  do away with the PPAs and adopt a licensing regime in the extension of  operations.
“If the IPPs disagree to the proposed renegotiation model, end the PPA when the time comes,” AWER added.
To  add more weight to the federal government’s position, AWER said IPPs  that reject the renegotiated terms must be blacklisted from any new  power generation projects, with the ban extended to its shareholders and  board of directors, their subsidiaries and parent companies and any new  companies or entities related to them.
AWER  also urged the government to open competitive bidding from Dec 1 this  year to allow for sufficient time to build the new power plants.
“The federal government must be firm in protecting the people’s interest and the country’s growth,” the association added.
No comments:
Post a Comment